Exiting times await local residents of Clyde North with the build on track for our new Clyde North Tuckers Road YMCA Early Learning Centre! We are thrilled to be getting the keys on November 30 and can’t wait to give local families a peep into what our Early Learning Centre will look like! All going well, we will be ready for tours early December.

Internal – what’s been completed
Final plastering on the inside is currently being completed and painting internally will commence later this week. Internal joinery and glazing will commence the week after.

External – Completed so far
The landscaping has commenced and paths have have been set around the ELC playground and surrounds! Fence posts are in and works to level out the play space is underway. Works on the ELC entrance and shared spaces will commence in early November.

Community build update
Ramlegh Spring residents will be keen to find that Ramelgh Boulevard has progressed! Concrete gutters are in and the sealing of the road is currently underway. The other side of Ramelgh is sealed with car parking on both sides.

Stay up to date with the latest news about our new Early Learning Centre.

Register your interest here.